Over the last week we have made excellent progress on redeveloping the 5th green-side bunker.

  • So far, a new drain has been created to help shed water from the area.

  • Imported around 30 large trailer loads of sub-base material to shape the area, equalling around 120 tonnes.

  • Shaped the bunker and banks, to continue the soft flowing slopes around the green.

  • Imported soil onto the area to prepare for Turfing over the next few days.

  • To maintain the momentum we currently have, we will begin stripping the sand / turf from the next bunker we plan to redevelop, the 5th

Thank you for your patience.

Kindest regards,

Windlesham Agronomy Team